News Archive
2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010

2009
Our Millwrights, Tom, Steve and Dave worked hard to complete the cap and it was finally lifted onto the mill on 29th November, despite a few setbacks with poor weather conditions the preceding week. The new cap is a work of art. The inner structure comprises 28 oak spars clad with horizontal pine boarding. These are then covered by vertical boards of red cedar, all meticulously chamfered into graceful curves.

A“time capsule” was placed inside the ball finial on the very top of the mill. This capsule contains various objects of current day interest and will be next seen by a future generation of cap restorers (which we hope won’t be required for a long time!). This is a time honoured tradition in milling circles.

We have installed a fully functioning toilet inside the mill, using an innovative and very sympathetic design. Richie has also worked his carpentry genius and constructed 4 grain bins using his own original design, whereby the bins encircle the central vertical shaft. This design enables us to maximise space for visitors while still being functional.

A “new” set of millstones has been installed. All the stones furniture has also been built and installed by our millwrights. These are truly beautiful, made of ash and pine and show that we are well on our way to becoming a fully working mill.

The new railings have been erected around the edge of the roundabout and the inside of the mill also received a lot of attention, with all the floorboards being replaced and the inside walls getting a well needed coat of whitewash. All of the 240 shutters for the sails have also been delivered - in kit form! We will soon begin the job of making these shutters to save us a lot of money. And finally, to improve access, handrails have been installed on the stairs which have made it much easier for visitors to climb up (and down) the mill.

Top


2008
Progress has not been as fast as we had hoped this year. The lime render round the base of the mill didn’t set properly in the bad weather so had to be taken off and re-applied by the Council. We are still waiting for this to “go off” before the tower can be painted black.

New floorboards have been laid on the Stones floor and a much needed new staircase from the ground floor has been put in. The millwrights have lifted the top stones on all four pairs so we could finally see the condition of the cutting surfaces. Unfortunately, it wasn’t pleasant viewing! Good news was on hand however, as our millwrights managed to find a “new” set of stones which we have used to replace our (soon to be) working pair.

There has also been excellent progress in restoring the ground floor machinery as the hurst frame, tentering gear and the kibbler have all been either restored or replaced. The cap is under construction and progress is steady. The fan stage and fantail are ready, as are the new shears. Wrought iron fence railings for the roundabout and handrails for the entrance steps have been ordered.

We have held six open weekends this year, attracting many locals and visitors to York alike. Many opted to join the society and we were thrilled with the huge number of compliments on our progress and on how impressive the mill looks.

In August this year, we celebrated reaching 500 members! Jen Hay’s enthusiasm has once again paid off through her very successful Open Gardens in July and Barn Dance in September. At the September open weekend, we held an Art Show for people to showcase items they’d made out of off-cuts of wood from the new floorboards. We had 35 entries and they received much admiration.

A gentleman living in Malvern, who had been cleaning out his loft, came across a bin bag full of old, historic documents, mainly about Acomb and Holgate. He sent us these documents, which are dated between 1774 and the late 1800’s. Many were conveyance documents, written in beautiful old script, but to us, the most interesting find among these documents was the original enclosure map of Acomb/Holgate in 1774, hand drawn with all the land owners names against their parcels of land. We can clearly see “George Waud” written on the small rectangle of land where the windmill stands. This would be only four years after the mill had been built. The documents have now been preserved in the York City Archives and would be of interest to anyone researching local history, although not to our mill itself, unfortunately.

Top


2007
The scaffolding and fencing was removed following the external renovation done by York Council. All the lime render has been applied to the outside walls and b
rand new solid oak doors and window frames have been fitted. Opening up the window apertures has allowed much more light to enter the mill and has brightened up all of the floors. Eric Daniels (Helens dad) has kindly made some shutters to protect the ground floor windows.

HWPS has finally signed the lease with York council, so the trustees are now officially in charge of Holgate Windmill! We have had a massive boost to our finances with a fantastic donation of £20,000 from York Conservation Trust.

In November, we held a sponsored 'Storming the walls' event, with many society members and friends walking round the city walls. This was a very high profile event and we raised £4,000 for the society. Santa also visited the mill on the first two weekends in December and was kept extremely busy handing out presents to hundreds of children, and raising £700 in the process.

2007 was a big year for raising funds. We secured nearly £98,000 from Grantscape, an environmental grant-making charity. This extra money means that we will be able to fully restore one set of stones and all the machinery required to drive them by wind power. We also secured a further £66,000 from The Esmee Fairburn Foundation this year. This will pay for the remaining work already underway to restore the cap and also allow us to put skeleton sail frames and fantail back on the mill. The cap is due to be returned to the mill in May.

The Heritage Lottery fund also gave us £50,000 to restore the ground floor. The Stones (1st) floor has been strengthened and this has allowed us to remove the 32 props which were holding it up. The ground floor now looks and feels much more spacious, giving more room to move around and view the machinery.
The council have completed work on the structure of the mill and it will be painted black when the weather improves.

Top


2006
October 2006 -
The City of York Council is making a very thorough repair to the outside of the Mill. The scaffolding is up and all the exterior black paint and concrete render has been removed. All brickwork has been repointed and strengthened and most of the new lime render has been applied. To complete the work it is essential to remove the cap and this was lifted off on 12th October using a large crane and transporter. It will be stored in a secure unit for about six months while it is being restored by Thompsons millwrights, so expect the mill to look barer than usual for a while.

Also as part of the restoration programme HWPS has ordered new windows and doors, mains power has been connected so we now have full lighting and power throughout the mill.

July 2006: Phase 1 of restoration works has started. The scaffolding has just been erected so the exterior brickwork and cap can be renovated and painted. The windows will also be re-instated, so the outside of the mill will regain it's traditional look with its distinctive black tar coating and white cap. Work has also recently commenced on getting a full electricity supply into the mill.

Feb 2006: The new fund raising campaign has already reaped rewards. Following our initial advertisements through the York Evening Press, we have had a lot of interest and have already had one very generous donation.

The society has purchased a corn dresser (a machine used by millers to seperate the finer grains from the coarse ones, through a sieve like system). It is a large machine, roughly 6ft long and 5ft high and is in really good condition so will be fantastic to use inside the mill.

Jan 2006: After our disappointing response from the Heritage Lottery Fund late last year, the society has launched it's new campaign to raise fund for the restoration. The society plans to significantly raise its profile over the coming year, both to raise awareness and funds.

Top


2005
July 2005:
After submitting our initial proposals to the Heritage Lottery Fund (HLF), we have had a disappointing first response, highlighting our problems with lack of facilities and space. The society is now looking at options suggested by HLF.

June 2005: The open weekend in May saw the mills doors opening to the public for over 75 years. Over 130 people turned up over the two days and we recruited 39 new members.

The society has just received a grant from the City of York Council to help us get mains power and lighting into the mill. Watch this space for further details.

April 2005: Last October, a group of society members braved the elements to plant 500 daffodil bulbs around the windmill to give it a splash of colour come spring time. Anybody who has been past the windmill in the last couple of weeks will have seen that the hard work has paid off with a host of golden daffodils surrounding the mill.

With the recent departure of Dr. David Hope to pastures new, we have been looking for a new patron. Following our search, we are proud to announce that our new Patrons are TV historian Adam Hart-Davis and local Look North presenter Harry Gration.

Top


2004
September 2004: Planning permission has been granted. The following press release has been issued to announce this fantastic piece of news:

"PRESS RELEASE

A residents group, which plans to restore and maintain York’s last remaining windmill, is celebrating the news that the City of York Council has granted Planning Consent for their venture.

Holgate Windmill Preservation Society was formed in 2001, to bring this local landmark back into full working order. Chairman Bob Anderton of Windmill Rise in Holgate said” Planning Consent will unlock the next stage of the development, by enabling us to complete arrangements for leasing the Mill for 15 years, from its owners, the City Council. This will fulfil the Heritage Lottery Fund’s minimum ownership conditions, and allow us to apply to them, for 90% of the estimated £400,000 restoration cost.”

Mr. Anderton continued “We hope to raise the balance from our own fundraising, with contributions from the business community and grant-making trusts. Restoration work could take up to 18 months. The Mill will then be opened to small, pre-booked parties.”

May 2004: Annual General Meeting held - Bob Anderton elected as new Chairman. Richard Green was re-elected as Vice Chair and Christine Bramwell was re-elected as Treasurer. Brian Lambert was also re-elected as secretary.

March 2004:
The official planning application has been submitted to the Council and a notice has been posted on the mill offering the public the 21 days to to register any opinions or objections.

February 2004: We have received a first draft of the document from the solicitors regarding the incorporation of the society. Incorporation is necessary to ensure that the society will be responsible for the windmill, and not the individual members of the committee.

January 2004:
Siginificant progress has been made on the architectural drawings of the mill so we now have a good idea of what it will look like when the work is finished. Once these drawings are completed, we will be in a position to submit a planning application to the City Council. But, before we attempt this, we intend to invite local residents to discuss the proposals with us, as we are very keen to get as much local support as possible. This project is intended to benefit the whole community and it is very important to us that people see this restoration as a positive improvement to the City.

Top


2003
September 2003:
The booklet on Holgate Windmill, as featured in the "York Evening Press" and the "York Star", has been printed and being sold to raise money. Educational workbooks have been commissioned which are based around the National Curriculum levels to teach children all about windmills. This will help to raise awareness of our cause within local schools and will hopefully be fun for the children to complete.
The millwrights estimate is a cost of approx. £400,000 to fully renovate the windmill so we will be looking for Lottery funding to help pay for this work.

August 2003:
The Council finished its structural work and the scaffolding has now been removed. Members of the committee have now been allowed access inside the mill for the first time. Funds are still coming in, with a successful day at the West Bank Park summer fayre. Several members of the committee recently visited four restored windmills:- Skidby Mill (the only other surviving Yorkshire windmill) and three others in Lincolnshire (Wrawby Post Mill, Ellis Mill and Waltham Mill) to get a perspective on the realities of running a windmill in the present day. Click here for more details of our day out.

A two page article on Holgate Windmill appeared in the September issue of the "Dalesman" magazine.

June 2003: The Council commenced its initial structural repair works. Scaffolding was erected around the mill. The Council have agreed that once this safety work is completed, the lease of the windmill will be transferred to the Society. The Society has invited quotations from four Millwright and Conservation firms with specific expertise in the restoration and repair of windmills, to initially carry out the full feasibility study of the works required to return Holgate Mill to operational use. This study will allow the society to more accurately evaluate the scope of the restoration works and the costs involved. It is anticipated that the successful Millwright will then be incorporated within the Society's professional team of Architects, Structural engineers and Quantity surveyors to produce detailed restoration proposals. These will, in due course, form the basis of Planning, Listed Building and Heritage Lottery Grant proposals.


March 2003:
We have applied to the Gannett Foundation (the charitable arm of Gannett Co. Inc, owners of the Yorkshire Evening Press) for funds for the feasibility study and should know in December whether we have been successful. Holgate Ward Committee have also contributed towards this feasibility study. Progress on the initial feasibility study has been hampered by the condition of the existing structure and condition of the mill. The City of York council have refused any access to the building until a full health and safety audit has been carried out. Structural engineers Scott Wilson were appointed by the Council to identify the condition of the mill and unfortunately, elements of both the internal and external structures were in worse condition than anticipated. These remedial works were needed as a first priority. The Council have a statutory obligation to carry out these works, as legal owners of the mill. Once these works have been carried out, representatives of the society and funding bodies will be able to access the building. The Charity Commission has accepted our application for charitable status and we are now Registered Charity No. 1096303.


2002: We have been successful in achieving a local Heritage Initiative award of £21,875 to cover the millwrights survey, to display promotional items, to set up an archive and to purchase a computer and software.

Top


 
Copyright HWPS