Holgate
Windmill Restoration Project
Breakdown of costs |
| Cleaning
Down |
£
800 |
| Timber
Inspection - Cap Only |
£
500 |
| Brickwork
To Tower |
£
10,800 |
| Door
& Windows |
£
6,500 |
| Electric
Lighting & Power |
£
5,000 |
| Fire
Detection & Alarm |
£
2,000 |
| Scaffolding |
£
5,000 |
| Chemical
Injected PDC |
£
1,000 |
| Water
& Plumbing |
£
2,500 |
| Lightning
Protection |
£
2,000 |
| Cap
Repair & Cladding Replacement |
£
15,000 |
| Exterior
Decoration (Inc Tar) |
£
11,000 |
| Works
To Stone Steps & Handrails |
£
1,000 |
| Preliminaries
(10%) |
£
6,200 |
| Contingencies
(10%) |
£
6,200 |
| Total
Cost (Excl VAT) |
£
74,500 |
| Total
Construction Cost (Excl VAT) |
£
74,500 |
| Architects
& QS Fees (12.5%) |
£
9,312 |
| CDM
Planning Supervisors Fees (1%) |
£
745 |
|
Project
Total (Excl VAT) |
£
84,557 |
|
VAT
Rated Repairs (£33,550) @ 17.5% |
£
5,871 |
|
Alterations
(£40,950) @ Zero |
NIL |
|
Consultants
(£ 10,057) @ 17.5% |
£
1,760 |
|
Project Budget
Total (Incl VAT) |
£
92,188 |