Holgate Windmill Restoration Project
Breakdown of costs

Cleaning Down
£ 800
Timber Inspection - Cap Only
£ 500
Brickwork To Tower
£ 10,800
Door & Windows
£ 6,500
Electric Lighting & Power
£ 5,000
Fire Detection & Alarm
£ 2,000
Scaffolding
£ 5,000
Chemical Injected PDC
£ 1,000
Water & Plumbing
£ 2,500
Lightning Protection
£ 2,000
Cap Repair & Cladding Replacement
£ 15,000
Exterior Decoration (Inc Tar)
£ 11,000
Works To Stone Steps & Handrails
£ 1,000
Preliminaries (10%)
£ 6,200
Contingencies (10%)
£ 6,200

Total Cost (Excl VAT)
£ 74,500

Total Construction Cost (Excl VAT)
£ 74,500
Architects & QS Fees (12.5%)
£ 9,312
CDM Planning Supervisors Fees (1%)
£ 745

Project Total (Excl VAT)
£ 84,557

VAT Rated Repairs (£33,550) @ 17.5%
£ 5,871
Alterations (£40,950) @ Zero
NIL
Consultants (£ 10,057) @ 17.5%
£ 1,760

Project Budget Total (Incl VAT)
£ 92,188