| 2006 |
|
| July |
Scaffolding erected |
| |
External black paint and
render removed |
| |
Bricked up windows &
door opened up |
| August |
Three phase electricity
supply installed |
| September |
New oak doors and windows
installed |
| |
Most of the external
renovation completed & new lime render starting to be applied |
| October |
Cap, brakewheel, iron
cross and shears removed |
| |
|
|
|
| 2007 |
|
| April |
Structural repairs to
first floor beams |
| |
Removal acro prop supports
for Stones floor (all 32 of them!) |
| May |
'York Stone' floor laid
on ground floor |
| June |
Restoration of ground
floor machinery and ironwork (ongoing to November 2007) |
| September |
New curb ring craned in |
| |
Scaffolding and Heras
fencing removed |
| |
Lime rendering of outer
walls completed |
| December |
Ground floor window shutters
installed |
| |
|
|
|
| |
|
| |
|
| |
|
| |
|
| |
|